Geismar 1 2026 TAR — DCS Scope Tracker INTERIM — FOR DISCUSSION

Interim · 12 Aug 2026, updated 14 Aug with the DCS meeting status (M. Smith, 13 Aug) · W. Vosloo · action A-17 (K. Kennedy / R. Partridge, due 14 Aug) · 💬 to comment, export via the Clarifications tab
3,090 h
DCS (1,790) + Instrumentation (1,300) in the P6 network — 14% of the 21,830 h TAR
0 / 132
W-15095986 activities with baseline dates — the #2 job on site is in the network but undated
6 WOs
DCS/I&E work orders in the Workbook, absent from P6 (0 h scheduled)
0 / 6
MOC threads approved — two of them are already scheduled for 16–17 Oct
3
DCS milestones in P6 with no date (1.2, 9.7, 9.8) — the only undated milestones
4d 8h
Min DCS float (Commission A531) vs 0d 2h on the stated critical path (W-14551438, MAC compressor KPM) — 16-Oct calendar
register rows checked ✓

General comments

Bottom line

The DCS scope is not missing from the schedule — it is invisible in it. W-15095986 (1,790 h, 132 activities) is in the P6 network with logic and float, but none of its activities carry baseline dates, so every date-filtered view drops it. The fix: date it, re-baseline, date the three DCS milestones, republish on the confirmed 16 Oct calendar.

A-17 cannot be closed as written: the big job is undated, six Workbook WOs have 0 h in P6, no MOC is approved, and the delivery → narrative freeze → configuration → FAT chain has no activities.

Findings — 💬 to raise a clarification against any finding

The gap, as one statement

In the P6 network: 3,090 h (DCS 1,790 + instrumentation 1,300). Not in the schedule: 6 WOs at 0 h — hours to be quantified by K. Kennedy. And 58% of the DCS hours that are "in" have no dates, so no defensible float.

How this gets worked — two passes, one register

Pass 1 · this dashboardWessel + MalcolmWalk the tabs, 💬 clarifications on findings, WOs and questions — each gets a TQ number.
ExportClarifications tabDownload .txt (meeting thread) or .csv (tracker sheet).
Pass 2 · the sheetTeam sessionKennedy, Partridge, Attuso, Picard answer each TQ in the sheet — owner, answer, date.
Close-outA-17 + re-baselineP6 republished on the agreed calendar; A-17 closes with the register as evidence.

DCS scope — work breakdown structure — six elements, gate-mapped; 💬 on each

DCS / I&E work order register — 💬 on any row to raise a clarification

P6 export 16 Jul (hours, floats, windows) · Workbook 17 Jul (flags, MOC) · floats on the 16-Oct calendar.

💬 WOGroupDescription P6 hPhaseWindow Min floatP6MOCFlagsQuick note

W-15095986 — Install new upgraded DCS for ASU 1 (1,790 h)

21 sub-jobs, 132 activities, PRE + TAR · FCO approved 9 Jun, moved to Workscope · cabinets CP0101, CP0108, FCP270/280, A501, A531, A541/543, A544, F533 · dashed red = no activities in P6.

Cabinet delivery
No delivery activity or Long-Lead tie in P6
Control narrative freeze
No milestone, no date
Configuration
No off-site config activities
FAT
Zero FAT activities in the export
PRE-TAR site prep — 218 h
Install CP cabinet A501 (28h) · E-stop wiring CtrlBldg→SwgrBldg (56h) · MCC I/O reroute (24h) · Edge switches (60h) · F533 retrofit start (50h) — milestone 1.2 "DCS PRE-TAR START" is undated
System Day 1 — 76 h
13 activities at TAR start — "DCS Outage" milestone 9.7 undated
Cabinet retrofits & I/O replacement — 458 h
A531 (62h) · A541/543 ×2 (98h) · A544 (54h) · Weidmuller I/O boards ×4 (200h) · E-stop/reroute continuations (44h)
Commissioning & loop checks — 1,038 h
Per cabinet: FBMs online → HART devices → loop checks. ~756 loops, run twice (Team 1 / Team 2). Tightest link: Commission A531-DCS-1, 222 h, min float 4d 8h. No crewing basis stated — may need around-the-clock loop-check crews.
BACK IN PIPE
1 Nov 19:00 (P6 calendar) — DCS Valve Outage milestone 9.8 undated

Sub-jobs (hours / activities / min float)

Sub-jobPhasehActsMin float

Does the DCS chain compute onto the critical path?

Not on the current numbers — but the numbers are not defensible. Stated path W-14551438 (MAC compressor 36M KPM) carries 0d 2h; the MAC feeder cable 0d 4h; the DCS job's tightest activity 4d 8h.

1. W-15095986's float rides on undated, unbaselined activities — one re-baseline could move it.
2. The 2 Nov date in the Workscope header is superseded — TAR start confirmed 16 Oct (12 Aug). Correct the Workbook.
3. The delivery → narrative → config → FAT chain has no activities: zero float visibility.

Float ladder — biggest jobs, min total float (16-Oct calendar)

Bars ranked at 8 h/day; values are P6 strings. 1,075 activities carry 1.0-unit placeholder labour.

The seven questions — where they stand after this pass — 💬 to add a clarification

Proposed actions — for the meeting — 💬 to amend before tabling

💬OwnerActionDue

Clarification register (TQ log)

Every 💬 lands here as a numbered TQ. Saved in this browser only — export before sharing. The .csv merges into the tracker sheet; the .txt goes to the meeting thread.

TQ #RefItemRaised byDateClarification / questionSuggested ownerStatus

No clarifications yet — use 💬 anywhere on the dashboard.

Clarification